What SCAQMD Rule 1403 Means for Your Demolition Project

igor kawalek • September 24, 2026

Share this article

The asbestos survey and the 10 working day notice that decide when your tear-down can start

If you are tearing down a house anywhere in Orange County, your schedule does not start with the excavator. It starts with an asbestos survey and a notification to South Coast AQMD. Rule 1403 sets both, and most owners find out about it about a week after they wanted to start.

Every demolition needs an asbestos survey first

Before any demolition or renovation, the building has to be surveyed for asbestos-containing material, and the survey has to be done by a Certified Asbestos Consultant (CAC) or a Certified Site Surveillance Technician (CSST). Not a contractor's judgement call, not a visual walkthrough: a signed survey report from a certified consultant.

In Orange County that usually means checking the places asbestos actually hides in housing built between the 1950s and the 1970s: mortar-bed tile and mastic, sheet vinyl and its backing, acoustic ceiling texture, drywall joint compound, roofing felts, duct wrap, and the paper facing on old insulation.

The 10 working day notice is what moves your start date

Once the survey is done, a notification goes to South Coast AQMD with the fee, and it is due 10 working days, or 14 calendar days, before work starts. Holidays push that out further. This is the single most common reason a tear-down slips: the crew is booked for next week and the notice has not been filed.

Plan it the other way around. Survey first, notification filed, then pick the start date.

Yes, even if the survey comes back clean

A clean survey does not remove the notification requirement. All demolitions require notification so that AQMD can inspect and confirm there is no asbestos in the building before it comes down. Testing clean is not a reason to skip the filing.

Asbestos comes out before the structure does

Where the survey does find asbestos, it is removed before demolition by a licensed abatement contractor, as its own phase with its own schedule. That is separate scope from the demolition, and you should see it as a separate line in your pricing rather than buried in a lump sum.

For renovations rather than tear-downs, the trigger is disturbing more than 100 square feet of intact asbestos-containing material. Below that, some removals are exempt, but the obligation to survey before the work does not go away.

Fees, revisions and cancellations

The fee goes with the notification, is based on the size of the project, and is not refundable. If your dates move, you file a revision, and if the revision puts the job in a higher fee category you pay the difference. Cancelling a notification is fee-exempt.

Move your dates twice and you have paid twice for the same job. It is another argument for locking the schedule down before filing.

The exceptions, and what they are not

Owner-occupants of a single-family home have limited exemptions and may do some of their own work, though other Rule 1403 requirements still apply. Those exemptions do not extend to condominiums, townhouses, or apartments.

Government-ordered demolitions can skip the 10-day wait with a written order, the survey report, and confirmation that the asbestos was removed. A tight construction schedule is not an emergency.

What this means for your timeline

For a standard Orange County tear-down, budget roughly three weeks from go-ahead to the first day of demolition: a few days to get a consultant out and get the report back, then the 14 calendar days of notice. Abatement, where it is needed, sits on top of that.

None of this is a reason to panic. It is a reason to call early. When we walk a property, two of the first questions we ask are who is doing your survey and whether the notice has been filed, because those decide when the house comes down, not the machine.

Planning a demolition in Orange County? Call Clear Path Demolition at (949) 603-3366 for a free walkthrough and clear pricing.

Recent Posts

By igor kawalek • October 14, 2026
A 1970s Orange County tear-out triggers lead and asbestos rules a 1990s one does not. What the 1978 and 1980 dates change, and what engineered framing costs you.
By igor kawalek • October 13, 2026
Orange County C&D recycling rules differ by city: diversion from 50 to 75 percent, thresholds, deposits and 30 to 90 day deadlines. What to check before you demo.
By igor kawalek • October 12, 2026
In a condo, townhome or apartment, an interior tear-out crosses federal asbestos and lead rules a detached house never touches, plus your HOA's own review.
By igor kawalek • October 11, 2026
Demolition counts as development under the California Coastal Act. What needs a coastal permit, when interior work is exempt, and how bluff lots change the job.
By igor kawalek • October 10, 2026
Rental turnover tear-outs in Orange County: the EPA lead rule, Cal/OSHA asbestos limits, the 30-day substantial remodel test, and what each one costs in time.
By igor kawalek • October 9, 2026
Tearing out a barn, stalls or corrals in Orange County? What treated wood, manure, arena footing and contaminated corral soil do to your scope and your budget.
By igor kawalek • October 8, 2026
Fire and water damage tear-out in Orange County: who does what, what the adjuster needs documented first, and the asbestos and permit rules that still apply.
By igor kawalek • October 7, 2026
Where Orange County demolition debris goes: the C&D and inert facilities, the city 65% ordinances, and the deposit rules that decide whether you get your money back.
By igor kawalek • October 6, 2026
Selective demolition or a full tear-down? The fire sprinkler, zoning, code, asbestos survey and debris triggers that decide it on an Orange County remodel project.
By igor kawalek • October 5, 2026
Plaster, lath and mortar-bed tile change what an Orange County remodel costs and how long it takes. What older homes hide behind the finishes and what to test first.
Show More